See this article with images in Slovak language.
Tag: pillars
Work done in 2017
The work season at Katarínka was finished with completion of almost all planned targets that were outlined in the article with the plan for season 2017.
Due to the fact that at the beginning of the season the tower was made available to public, the work in it was adjusted to avoid disturbing the guided visits. We were pointing windows arches and jambs on the first and second floor of the tower, mainly from the outer side (see picture comparison below).
The head of the pillar in the north-east corner of the church nave was repaired and grassed over. Next to it, there is the last remaining pillar that will be repaired the next season. In both the interior and exterior of the church, plasters were being fixed and holes filled with mortar, including the entry to the tower.
The southern chancel wall was deeply re-pointed from both sides, its top was disassembled and masoned anew. The masonry at the top was covered with a clay layer covered with grass clumps in order to protect the new mortar from frost and other weather conditions (see picture comparison below).
In the monastery, the work was carried out mostly in the last three cells and in the corridor. The work included pointing, fixing of plasters and repairing jambs of doors and windows.
Archaeology was carried out on a large scale; the entrance to Erdődy crypt and its side wall were discovered. During the excavation for lightning conductor, pieces of floor were found in the church nave and the pedestal of big Calvary statue (that was after the monastery dissolution moved to Dechtice) was discovered to the left of the monastery entrance.
In the middle of summer, during the weekend July 21-23, the long awaited lime slaking was done; the lime hole was filled with nine tons of lime. After the season, in autumn, window shutters were installed to protect the 5th tower floor from snow and rain.
Work plan 2017
This article is available only in Slovak language.