Work done in 2017

The work season at Katarínka was finished with completion of almost all planned targets that were outlined in the article with the plan for season 2017.

Due to the fact that at the beginning of the season the tower was made available to public, the work in it was adjusted to avoid disturbing the guided visits. We were pointing windows arches and jambs on the first and second floor of the tower, mainly from the outer side (see picture comparison below).

The head of the pillar in the north-east corner of the church nave was repaired and grassed over. Next to it, there is the last remaining pillar that will be repaired the next season. In both the interior and exterior of the church, plasters were being fixed and holes filled with mortar, including the entry to the tower.

The southern chancel wall was deeply re-pointed from both sides, its top was disassembled and masoned anew. The masonry at the top was covered with a clay layer covered with grass clumps in order to protect the new mortar from frost and other weather conditions (see picture comparison below).

In the monastery, the work was carried out mostly in the last three cells and in the corridor. The work included pointing, fixing of plasters and repairing jambs of doors and windows.

Archaeology was carried out on a large scale; the entrance to Erdődy crypt and its side wall were discovered. During the excavation for lightning conductor, pieces of floor were found in the church nave and the pedestal of big Calvary statue (that was after the monastery dissolution moved to Dechtice) was discovered to the left of the monastery entrance.

Krypta 2017

In the middle of summer, during the weekend July 21-23, the long awaited lime slaking was done; the lime hole was filled with nine tons of lime. After the season, in autumn, window shutters were installed to protect the 5th tower floor from snow and rain.

 Hasenie vápna 2017

Working season 2016 update

The work season on Katarínka is already slowly going to its end. The so-called búračka is taking place, i.e. the camp is taken apart and stored until the next year, when it will be put together again. Currently (in the week between 29th August and 4th September), there is approximately 50 to 60 young volunteers present…

Considering work, it is mainly about realising tasks that were mentioned in advance in the previous news that covered the work plan for year 2016.

It was necessary to restore the capitals of the pillars (picture on the left) while moving the scaffolding multiple times in the nave of the church, as there are 8 pillars in it.


The work on the reconstruction of the segmental arch, which was mainly done in the middle of August this year, is being finished (picture on the left). In the picture on the right, there are two young masons, who underpin one of the walls of the monastery to avoid a possible fall of the wall that could happen otherwise.

 

In the chancel (picture on the left), south-eastern wall was renewed by filling in missing stones and conserving its stable parts.

In the south-western part, the wall was recreated only from bricks, without any wet binder (picture on the right). The reason for not using groat on this wall is that we can not precisely estimate in which way the wall from the chancel continued. This will have to be discovered by the historical and archeological exploration in the future.

 

The last carpenter and conservation works in the tower are being finished. More detailed information concerning the opening of the view tower of the church will be published in September or October.